Project Status‎ > ‎

Project Timeline

Initial construction preparation started Spring 2015 and is expected to complete by 2018 -- our 150th year!

Detailed Timeline

 Milestone  

 Expected 

 Notes

 Construction approval March 2015    The congregation approves start of construction process as funds are available. 
 Oil tank removal  May 2015Oil tank was removed.
 Store removal  Summer 2015Stores were demolished over the summer.   Grounds have filled, and grass planted.
 Repair & Painting of Education Building Summer 2015External areas of the existing Wesley Education Building were painted and repaired.
 Walkway to rear installed Fall 2015City of Nashua to install a walkway along the south side of the property to enable access from Main St to Spring St parking.
 Sidewalks upgraded Fall 2015City of Nashua upgraded the Main St sidewalks in front of the church as part of the downtown improvements. 
 Heart of Nashua: Growing in Faith Campaign Fall 2016 A second capital campaign launches to fully underwrite the full renovation project.
 Groundbreaking   tbd Construction awaiting sufficient funding.